On 15/11/22 the Council, in exercise of the powers conferred on it by Section 14(1) of the Road Traffic Regulation Act 1984, as amended, and of all other enabling powers, made the above-named Order, to allow BT Network upgrade works
Clunch Road closed form its junction B769 to its junction A77
The Order commences on Monday 28th November 2022 and has a maximum duration of 18 months or until the works are completed, whichever is earlier. The works are expected to commence from 08:00hrs on Monday 28th November until 18:00hrs on Friday 9th December 2022 and the Order will be implemented only when appropriate signs are displayed.
Vehicular access for residents/owners/occupiers within the closure will be permitted to and from their properties. This may on occasion be via the diversion route.
Emergency access will be maintained at all times during the road closures via the diversion route
Alternative Route: will be signed via – Cutstraw Road, B778, Clunch Road, A77, B778, B769 and vice versa
Kevin Braidwood
Head of Roads - Ayrshire Roads Alliance
Opera House
8, John Finnie, Street,
Kilmarnock
KA1 1DD
Email: enquiries@ayrshireroadsalliance.org
Tel: 01563 503160
Road Traffic Regulation Act 1984, as amended, and of all other enabling powers